|
Date |
Description |
|
March 2004 |
 |
Preparation for construction began with the relocation of the Robert Packer
Hospital Gift Shop, the Robert Packer Hospital Emergency Department entrance
and some hospital service departments. All patient and visitor traffic to
the Sayre campus was shifted to the Clinic Atrium entrance. |
|
April 2004 |
 |
On April 2, the groundbreaking ceremony was held for the new surgery
building. Site demolition began April 12, and the drilling of building
support pilings began soon after. The building grid was laid out in late
April, and floor levels between the existing building and new building
location were verified. A new helipad was created on the north side of
hospital as the existing helipad will be inaccessible during construction. |
| May 2004 |
|
 |
Drilling the pilings that will support the entire surgery building began in
May. More than 300 pilings, drilled by a machine called an auger-cast pile,
will hold up the completed surgery building. An auger-cast pile is a
structural support column created by forcing high-strength grout down the
center of an auger bore as a hole is drilled in the ground. This type of
piling is required in areas with marshy ground to ensure the stability of
the support piling. The surgery building pilings are each 16 inches in
diameter and are drilled to a depth of 49 or 65 feet. |
|
June 2004 |
 |
Construction work continued in June, including excavation of the elevator
pits, creation of the retaining wall (including waterproofing), and placing
piling caps. Concrete slabs were poured for the lowest level of the
structure. |
|
July 2004 |
 |
After pilings and slab work were complete, steel began to shape the new
surgery building. The steel-setting crane arrived on campus this month, and
watching the steel climb higher was especially exciting when 60-foot beams
were lifted into place outside the cafeteria!
Underground utilities were installed this month, and site grading was
completed.
|
|
August 2004 |
|
 |
In August, the tunnel connecting the service side of the campus with the
patient care side of campus was closed for several consecutive weekends to
allow a trench to be dug in the tunnel. This trench will accommodate cables
that connect two new generators in the RPH Power Plant to the new surgery
building to provide emergency power. Steel setting continued this month.
|
|
September 2004 |
 |
The first of six air handlers for the new building arrived. |
| October
2004 |
 |
On October 8, Guthrie physicians, administrators and staff celebrated the
"topping out" of the new surgery building. Topping out refers to the
placement of the highest beam of a structure and signifies that major
steelwork is complete. Topping out is a long-standing building tradition. It
can involve simply securing the final beam, or can be a more elaborate
ceremony that includes tying a small evergreen tree and American flag to the
beam once in place. In ancient cultures, placement of a tree on the top beam
was intended to honor the trees that provided the wood for construction. |
|
At the surgery building topping out, a live evergreen tree was used; at the
completion of construction, it will be planted on site as part of the new
building’s landscaping as a symbol of growth and change. The American flag
placed during the ceremony will be flown on top of the building for the
duration of the project. Guthrie employees and physicians had the
opportunity to sign the topmost beam prior to the ceremony in order to
symbolically become a permanent part of the new building.
In mid-October, installation of vertical steel channels was started. These
channels will support the external "skin" of the building. Other major
portions of surgery building construction that were well under way in
October included masonry, decking and detailing, exterior metal framing,
construction of the elevator penthouse (where controls are housed) and roof
installation. Pouring of concrete decking was also initiated. Guthrie's Pain
Services Department was relocated to the 4th floor main to make room to join
the new building to the existing Clinic building. |
| November
2004 |
|
 |
This month, work began to break through onto the fourth floor of the
existing Clinic East Building from the new surgery building. Floor and roof
decking were completed, fireproofing began and continued weather-permitting,
and installation of the new Atrium elevator car started. |
|
December 2004 |
 |
On December 9, Guthrie Sayre campus staff celebrated the 175th day of
construction work -- the halfway point -- on the new surgery building with a
Halfway There party. Physicians and staff were treated to cake and punch in
the RPH Cafeteria, and had the opportunity to meet Guthrie construction
staff and contractors to ask questions. RPH President Bill Vanaskie also
addressed attendees. Cake was also served to construction tradespeople
working on the jobsite. Also in December, the building wrap was completed,
exterior brickwork began, and work continued on inside projects such as
mechanical, electrical and plumbing on all floors. |
|
January 2005 |
 |
The
exterior of the surgery building began to take definite shape this month --
it's now easy to see what the completed structure will look like. Work
continues on studding, plating, fireproofing, bricking, mechanical,
electrical, plumbing, door frames and duct work. |
|
February 2005 |
 |
This month marked the completion of gypsum board installation in the new
central processing area and the beginning of the finishing process in this
area. Medical gas piping and rough-ins for nurse call and the sprinkler
system began on the fourth floor. Installation of gypsum board started in
the minor surgery rooms and the ambulatory surgery space. Transition teams
began to meet to determine how occupation of the new building will occur. |
|
March 2005 |
 |
Work continued
steadily through March. Supports for OR booms, louvers in the elevator
penthouse, exhaust ducts on the second level, and rails in the clean, soiled
and passenger elevator cars were all installed in early March.
Mechanical, electrical and plumbing work
continued on the fourth floor. The final stages of sprinkler piping on first
floor were completed, Ambulatory Surgery rough-ins were completed and by
late March, brickwork on the main exterior portion of the surgery building
was finished. Electrophysiology Lab renovations were completed, and steel
for the Clinic’s South Atrium entrance canopy arrived and was installed.
|
|
The big event in March took several days mid-month: The cable that will
supply emergency power to the surgery building was pulled from the generator
in the RPH Power Plant through the trench in the tunnel to the new surgery
building. |
|
April 2005 |
 |
In April, work
resumed on the surgery building roof once temperatures remained steadily in
the 40s. Mechanical, electrical, plumbing and fireproofing work continued;
gypsum board installation was nearly complete in the fourth level ambulatory
surgery section. All but one operating room was studded by the end of April.
Ductwork will continue until July. Steel for the helipad arrived midmonth
and was installed. In late April, site work began, including grading and
paving. |
|
May 2005 |
 |
In May,
Guthrie accepted delivery of a variety of large equipment for the surgery
building. The building's emergency generator went online, and the
mechanical, electrical and plumbing in the reception area reached 99%
completion. Ceiling installation was completed in two of the operating
rooms. |
|
June 2005 |
 |
The shell
space for the future operating room expansion was closed in. Window
installation was completed, as was ceramic tile installation. Painting was
largely complete by the end of June.
|
|
July 2005 |
 |
In July, the
roof was completed and windows sealed. Site paving began, and portions of
the parking lot closest to the South Clinic Atrium Lobby entrance were
striped. Central Processing occupied its new space in the lowest level of
the surge. |
|
August 2005 |
 |
In August,
mechanical systems throughout the building were up and running. Floors
throughout were sealed with an epoxy coating in preparation for the
installation of sheet vinyl. Contractors began to remove their trailers from
the worksite, and phone, cable and power lines were shifted to accommodate
helicopter landings resuming on the south side of campus. Sidewalk pouring
was completed. |
|
|
|
|
September 2005 |
|
|
In September,
the installation of new flooring began in the Clinic Atrium Lobby. Portions
of the composite panelling for the South Atrium entrance canopy were
installed, and floor installation continued in the surgery building itself. |